Skywatch June 2010 - Skycourts official newsletter

Highlights of Skywatch June 2010 - Skycourts official newsletter

  • Skycourts opens customer service centre in preparation of the project handover
    600-5222-60
  • New Skycourts website launched: http://www.skycourtsdubai.com
  • Scheduled delivery: Second half of 2010

Wednesday, January 27, 2010

‘SKYWATCH’ The First Official Newsletter for Skycourts update

‘SKYWATCH’ The Official Newsletter for Skycourts update has been published.

Highlight (an excerpt from the newsletter)
“The Skycourts project is undergoing rapid progress. The handover will be based on completion of individual towers and we expect the handover for all six towers to be completed by the third quarter of 2010”

GKB

Tuesday, January 12, 2010

Skycourts Update 9th January 2010

The new thing to watch in 9th January update pictures is that the outside parking paneling has commenced from Tower A, other the pack of tiles placed behind the building seem like interlock bricks, that means the landscaping would start soon.

All towers have reached canopy level. It seems 90% of glass paneling for Tower A has finished, followed by Tower D and then others.

Government seems to be seriously developing the community since more street and traffic lights have come up. Also the vicinity is buzzing with construction activity. The building behind Skycourts is almost finished with other buildings near by under way.